Time calculation to predict end time
- 3 years ago
I hope this works, I just divided Cycle Time by 24 (here 24 is hours in a day)
Hi Pricef1 ,
You can do this in M query but before that you need to have Date and Time columns combined.
After combining it, create a custom column in M query as:
= [Date] + #duration(0,0,0,27000)
--here 27000 is in seconds (7.5 hours)
Result:
Thanks,
Hamed
- Pricef13 years agoRegular Visitor
Is there a way to have it update automatically? For example not all cycle times are the same. Could vary from 6hrs to 7.5hrs depending on product. Time in * Cycle Time / ?????? maybe?
- HamedM11253 years agoAdvocate III
I hope this works, I just divided Cycle Time by 24 (here 24 is hours in a day)
- Pricef13 years agoRegular Visitor
Modified just slightly and it gave me the exact times I was looking for!! Thank you for your help
- Pricef13 years agoRegular Visitor
Or would i need to somehow convert cycle time in a seperate column and then refence that column?