Stopping a Cumulative Earned Value Measure at a Certain Point
Hi,
I need some help stopping my Cumulative Earned Value measure to stop at a certain Week Ending.
See below snippet.
I have drawn a red line on where I need the earned value line should stop. I need it to be stopped on the Week Ending 01/09/2023, have tried a couple of things but they all seem to just strertch the graph out and become a straight line.
I also have the Data Table linked to the Calendar Milestone table.
Below is the current formula being used.
Thank you 🙂
In your Calendar table add a column called CurrentWE
CurrentWE = CALCULATE(MAX('Calendar'[Week Ending]), Filter('Calendar', 'Calendar'[Date] = TODAY()))Then the new RunningTotal Measure
Cumulative EV Labor = VAR MaxDate = MAX('Calendar'[Date]) RETURN CALCULATE([Earned Labor], KEEPFILTERS( 'Calendar'[Date] <= MaxDate && MaxDate < = 'Calendar'[Current WE] ), ALL('Calendar'))Thanks
Joe
If this post helps, then please Accept it as the solution
13 Replies
- JoeBarry
Solution Sage
In your Calendar table add a column called CurrentWE
CurrentWE = CALCULATE(MAX('Calendar'[Week Ending]), Filter('Calendar', 'Calendar'[Date] = TODAY()))Then the new RunningTotal Measure
Cumulative EV Labor = VAR MaxDate = MAX('Calendar'[Date]) RETURN CALCULATE([Earned Labor], KEEPFILTERS( 'Calendar'[Date] <= MaxDate && MaxDate < = 'Calendar'[Current WE] ), ALL('Calendar'))Thanks
Joe
If this post helps, then please Accept it as the solution
- Dylo_BloomfieldFrequent Visitor
Thanks Legend, Worked a Charm!!!
- Dylo_BloomfieldFrequent Visitor
JoeBarry just quickly I have noticed that the Earned Valuee line isn't going through to the 29/08/2023.
See Below.
What could be the error resulting in this?
Thanks Joe
- JoeBarry
Solution Sage
I think I know the error, can you change the part of the code from
< = 'Calendar'[Current WE] ),
to <= there is a space between them and it shouldn't be like this.
Also confirm that the CurrentWE date is 05/09/2023
Also check if the Cumulative forecast measure isn't covering the line. it may do if they have the same values. Just remove it from the visual for the moment.
Let me know if this helps