Hello legolasladlf ,
this function will return all the working days between your start and end dates:// fnWORKINGDAYS let func = (StartDate, EndDate, optional Holidays as list, optional StartOfWeek as number) => let /* Debug parameters StartDate = #date(2022,10,7), EndDate = #date(2022,10,23), Holidays = null, StartOfWeek = null, */ // optional StartOfWeek, if empty the week will start on Monaday startOfWeek = if StartOfWeek = null then 1 else StartOfWeek, // cater for empty dates StartEmpty = if StartDate = null then #date(1900,1,1) else StartDate, EndEmpty = if EndDate = null then #date(1900,1,1) else EndDate, // Providing for logic where EndDate is after StartDate Start = List.Min({StartEmpty, EndEmpty}), End = List.Max({StartEmpty, EndEmpty}), // Switch sign if EndDate is before StartDate Sign = if EndEmpty < StartEmpty then -1 else 1, // Get list of dates between Start- and EndDate ListOfDates = List.Dates(Start, Number.From(End - Start) + 1,#duration(1,0,0,0)), // if the optional Holidays parameter is used: Keep only those dates in the list that don't occur in the list of Holidays; // otherwise continue with previous table DeleteHolidays = if Holidays = null then ListOfDates else List.Difference(ListOfDates, List.Transform(Holidays, Date.From )), // Select only the first 5 days of the week // The 1 in the 2nd parameter of Date.DayOfWeek makes sure that Monday will be taken as first day of the week DeleteWeekends = List.Select(DeleteHolidays, each Date.DayOfWeek(_, startOfWeek) < 5 ) in DeleteWeekends ,documentation = [ Documentation.Name = " Date.Workdays.pq ", Documentation.Description = " Returns the dates of the working days between StartDate and EndDate. ", Documentation.LongDescription = " Returns the dates of the working days between StartDate and EndDate. Working days exclude weekends and any dates identified in (optional) holidays. ", Documentation.Category = " Date ", Documentation.Source = " www.TheBIccountant.com . ", Documentation.Version = " 1.0", Documentation.Author = " Imke Feldmann ", Documentation.Examples = {[Description = " ", Code = " ", Result = " "]}] in Value.ReplaceType(func, Value.ReplaceMetadata(Value.Type(func), documentation))If you apply it on the rows of your table, you'll get a list of all the relevant dates. Before expanding it, you should add a column that counts the number of rows of this list, as this will be the divisor for the FTE-calculation.
Please let me know if you need further help with implementing this solution.
Hello legolasladlf ,
this function will return all the working days between your start and end dates:
// fnWORKINGDAYS
let func =
(StartDate, EndDate, optional Holidays as list, optional StartOfWeek as number) =>
let
/* Debug parameters
StartDate = #date(2022,10,7),
EndDate = #date(2022,10,23),
Holidays = null,
StartOfWeek = null,
*/
// optional StartOfWeek, if empty the week will start on Monaday
startOfWeek = if StartOfWeek = null then 1 else StartOfWeek,
// cater for empty dates
StartEmpty = if StartDate = null then #date(1900,1,1) else StartDate,
EndEmpty = if EndDate = null then #date(1900,1,1) else EndDate,
// Providing for logic where EndDate is after StartDate
Start = List.Min({StartEmpty, EndEmpty}),
End = List.Max({StartEmpty, EndEmpty}),
// Switch sign if EndDate is before StartDate
Sign = if EndEmpty < StartEmpty then -1 else 1,
// Get list of dates between Start- and EndDate
ListOfDates = List.Dates(Start, Number.From(End - Start) + 1,#duration(1,0,0,0)),
// if the optional Holidays parameter is used: Keep only those dates in the list that don't occur in the list of Holidays;
// otherwise continue with previous table
DeleteHolidays = if Holidays = null then ListOfDates else List.Difference(ListOfDates, List.Transform(Holidays, Date.From )),
// Select only the first 5 days of the week
// The 1 in the 2nd parameter of Date.DayOfWeek makes sure that Monday will be taken as first day of the week
DeleteWeekends = List.Select(DeleteHolidays, each Date.DayOfWeek(_, startOfWeek) < 5 )
in
DeleteWeekends
,documentation = [
Documentation.Name = " Date.Workdays.pq ",
Documentation.Description = " Returns the dates of the working days between StartDate and EndDate. ",
Documentation.LongDescription = " Returns the dates of the working days between StartDate and EndDate. Working days exclude weekends and any dates identified in (optional) holidays. ",
Documentation.Category = " Date ",
Documentation.Source = " www.TheBIccountant.com . ",
Documentation.Version = " 1.0",
Documentation.Author = " Imke Feldmann ",
Documentation.Examples = {[Description = " ",
Code = " ",
Result = " "]}]
in
Value.ReplaceType(func, Value.ReplaceMetadata(Value.Type(func), documentation))
If you apply it on the rows of your table, you'll get a list of all the relevant dates. Before expanding it, you should add a column that counts the number of rows of this list, as this will be the divisor for the FTE-calculation.
Please let me know if you need further help with implementing this solution.