Microsoft Fabric Community Conference 2025, March 31 - April 2, Las Vegas, Nevada. Use code FABINSIDER for a $400 discount.
Register nowGet inspired! Check out the entries from the Power BI DataViz World Championships preliminary rounds and give kudos to your favorites. View the vizzies.
Dear All.
Good Day.
I have created a calculated measures and when I use it in my table, it looks fine.
It is the allocated expense for project and in my table it filters the projects correctly and looks nice.
But when I use slicer option to choose an specific project code, it stops filtering and the data disappears.
Why?
wht is the difference of slicer with table that one can filter my measure while another can't.
I used the same field "project code" for both visuals and checked it.
here is two pictures. first the table without slicer, second the table with slicer which is not working.
I'd be happy to hear your advice.
Regards,
Amin Khaghani
Solved! Go to Solution.
Hi, @Amin_Adham
You can try the following methods.
Measure = [Percent of Total]*CALCULATE([Overhead],ALL('00- JV List'),ALL('01- Project Hours'))
Is this the result you expect?
Best Regards,
Community Support Team _Charlotte
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi Dear v-zhangti and many thanks for the help.
I entered the mentioned formula in my original report and it's now working fine.
THanks
Hi @Amin_Adham
Looking at your images, it appears that the slicer is working correctly, assuming that there is no data associated with the Project Code -1987.
I'm not sure what you expect to see when the code -1987 is selected?
Hard to give you any other advice without seeing your PBIX file - please provide a copy with anonymized data if the data is sensitive.
Regards
Phil
Proud to be a Super User!
Hi Dear Philip.
Hope you are doing well and many thanks for your time and responde.
I have created a test sample with all fake data and have attached for your kind attention.
Please refer to the last sheet, named: "Test".
There you can see that I have a Project list that each have it's allocated Overhead expenses.
beside I added an slicer to filter any specific project. but when I choose a project code, the calculations and filters disappera.
For sure, they have data and I checked.
for example: Project 1281 hase an overhead amount of 150 M, but when clicking on Project 1281 in slicer, It disappears.
I have copied the download link for the pbix file.
https://www.dropbox.com/s/m9ounkccidtripc/01-%20Allocation%20Test.pbix?dl=0
Please check and advise.
Best Regards,
Amin
Hi, @Amin_Adham
You can try the following methods.
Measure = [Percent of Total]*CALCULATE([Overhead],ALL('00- JV List'),ALL('01- Project Hours'))
Is this the result you expect?
Best Regards,
Community Support Team _Charlotte
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
March 31 - April 2, 2025, in Las Vegas, Nevada. Use code FABINSIDER for a $400 discount!
Check out the February 2025 Power BI update to learn about new features.
User | Count |
---|---|
84 | |
69 | |
66 | |
50 | |
32 |
User | Count |
---|---|
116 | |
99 | |
75 | |
65 | |
40 |