Scoring overall completion

I have Table A with Workpack List. Table B shows link of Work pack to documents with their status 'Completed" or "In progress". I want to have a visual which give me the completion score of each work pack. if all documents linked to a work pack are completed, the workpack score is 100%. example as below.

 

Table1  Table2    Report   
Workpack  WorkpackDocDoc StatusForecast Date WorpackOverall Status    Doc Count latest Doc date
A  AFFComplete  A100%4 
B  AGGComplete  B25%515/10/2023
   AHHComplete      
   BRRComplete      
   BHHIn Progress5/05/2023     
   BTTComplete      
   BOOIn Progress10/05/2023     
   BPPIn Progress15/10/2023