SUMIFS Problem

Ho together,

 

I´m new at PBI and look for an aquivalent for the Sum IF Function in Excel:

 

I have to tables. 1. one is calles "KontElement" and contains the columns [CSAuftrag] and [Budget].

The 2. one contains several operations per each CS-Auftrag Number.

 

CSAuftrag   Budget

1                  40

2                  50

 

 

Table 2:

 

CsAuftrag    Leistung

1                   5

1                   7

2                   9

1                   8

2                   9

2                   4

 

 

 

What I want to have:

 

CSAuftrag   Budget    Leistung (Sum!)

1                   40           20

2                   50           22

 

 

Anybody who can help me, I´m kind of lost right now... =(

 

Greetings,

Fel

  • Hi BachFel

     

    You can use this calculated column in Table 1 i.e. KontElement

    Assuming 2 tables are related on column CSAuftrag

     

    =
    CALCULATE ( SUM ( Table2[Leistung] ) )
    

     

  • Hi BachFel

     

    Looks good to me. May be I am missing something

     

    Could you show what you are getting and what you expect?

  • Hi BachFel

     

    Try this

     

    WorkingTime_Jan =
    CALCULATE (
        SUM ( LN[ArbeitszeitInH] ),
        FILTER (
            VALUES ( LN[Dates] ),
            MONTH ( LN[Dates] ) = 1
                && YEAR ( LN[Dates] ) = 2018
        )
    )
    

5 Replies

  • Zubair_Muhammad's avatar
    Zubair_Muhammad
    Community Champion

    Hi BachFel

     

    You can use this calculated column in Table 1 i.e. KontElement

    Assuming 2 tables are related on column CSAuftrag

     

    =
    CALCULATE ( SUM ( Table2[Leistung] ) )
    

     

    • BachFel's avatar
      BachFel
      Helper II

      Hi Zubair_Muhammad

       

      the two table are related. They are related on column KontElementID, which is also good?

      But the calculated numbers are wrong..

       

       

      I created following calculated column:

       

      IstLeistung = Calculate ( Sum (LN[ArbeitszeitInH])
      • Zubair_Muhammad's avatar
        Zubair_Muhammad
        Community Champion

        Hi BachFel

         

        Looks good to me. May be I am missing something

         

        Could you show what you are getting and what you expect?