Hi guys,

 

I'm stuck in a situation, I need calc a Planned Value of a project what has 25 months of duration. 
to calc the planned value I need to know how much each month equivale in percentage about the total.

Exemple The Project has 25 months, in the second month it should be 8% completed in the third 12%.

 

Thanks,

 

Felipe

1 ACCEPTED SOLUTION
Anonymous
Not applicable

Hi @ftorres,

 


I think what you need is to count the months till the desired period of that project and then divide that by ALL months of the project.

 

This shouldn't be a hard measure but I need some sample data to make a concrete example.

 

Kind regards,

View solution in original post

1 REPLY 1
Anonymous
Not applicable

Hi @ftorres,

 


I think what you need is to count the months till the desired period of that project and then divide that by ALL months of the project.

 

This shouldn't be a hard measure but I need some sample data to make a concrete example.

 

Kind regards,

Helpful resources

Announcements
November Power BI Update Carousel

Power BI Monthly Update - November 2025

Check out the November 2025 Power BI update to learn about new features.

Fabric Data Days Carousel

Fabric Data Days

Advance your Data & AI career with 50 days of live learning, contests, hands-on challenges, study groups & certifications and more!

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.

Top Solution Authors
Top Kudoed Authors