Hi guys,
I'm stuck in a situation, I need calc a Planned Value of a project what has 25 months of duration.
to calc the planned value I need to know how much each month equivale in percentage about the total.
Exemple The Project has 25 months, in the second month it should be 8% completed in the third 12%.
Thanks,
Felipe
Solved! Go to Solution.
Hi @ftorres,
I think what you need is to count the months till the desired period of that project and then divide that by ALL months of the project.
This shouldn't be a hard measure but I need some sample data to make a concrete example.
Kind regards,
Hi @ftorres,
I think what you need is to count the months till the desired period of that project and then divide that by ALL months of the project.
This shouldn't be a hard measure but I need some sample data to make a concrete example.
Kind regards,