Forum Discussion
Required production rate calculation
Hello Team,
My power bi data as attached below.
I would like to calculate the required production rate for remaining working dates of the month.
I would like to have measure for
Required rate = (sum of plan - sum of production qty)/remaining days
Current rate = (sum of production qty)/worked days
Can you please support?
Pbix file link
Current rate and required rate.pbix
Hi,
I have done this way
Required rate = DIVIDE(([Plan sum]-[Actual]),[REMAIN])
Current rate = DIVIDE(([Test MTD actual sum]),[Worked days])
It working fine for me 🙂
3 Replies
- amitchandak
Super User
Karthik12 , For the current month or use max(Date[Date]) in place of today()
Working Dates of month = networkdays(eomonth(today(),-1)+1, eomonth(today(),0) )
Working Dates of passed= networkdays(eomonth(today(),-1)+1, today() )
Working Dates of left= networkdays(today() +1 , eomonth(today(),0) )
MTD Today =
var _min = eomonth(today(),-1)+1
var _max = today()
return
CALCULATE([Net], FILTER('Date','Date'[Date] >=_min && 'Date'[Date] <= _max))This Month Today =
var _min = eomonth(today(),-1)+1
var _max = eomonth(today(),0)
return CALCULATE([Net], FILTER('Date','Date'[Date] >=_min && 'Date'[Date] <= _max))- Karthik12
Post Patron
Thanks !
Can you check my file and help for the below?
I would like have measures for below both
Required rate = (sum of plan - sum of production qty)/remaining days
Current rate = (sum of production qty)/worked days
Please refer my pbix file link.
- Karthik12
Post Patron
Hi,
I have done this way
Required rate = DIVIDE(([Plan sum]-[Actual]),[REMAIN])
Current rate = DIVIDE(([Test MTD actual sum]),[Worked days])
It working fine for me 🙂