Hi,      I have a table (TaskTimePhasedDataSet) that has time phased project data. The table measures project performance over time, akin to the "Earned Value Over time" report in Microsoft Project....
  • Anonymous's avatar
    Anonymous
    9 years ago

    Hi Lenin,

    You may need to create measure to calculate SPI when the TimeByDay equals to Project Status Date, then create Line Chart using the measure. You can share sample data of your tables or PBIX file for us to analyze.