Report Level Filter Based On Formula
- Anonymous9 years ago
Hi Lenin,
You may need to create measure to calculate SPI when the TimeByDay equals to Project Status Date, then create Line Chart using the measure. You can share sample data of your tables or PBIX file for us to analyze.
Thanks,
Lydia Zhang
Hi Lydia,
I was seeking to be able to show data on the line chart up to the "Project Status Date" which is set on my table. I wanted this to happen automatically i.e. when I select a project from my drop down the line chart only shows data up to the "Project Status Date".
Sorry if this is not clear.
Lenin
Hi Lenin,
You may need to create measure to calculate SPI when the TimeByDay equals to Project Status Date, then create Line Chart using the measure. You can share sample data of your tables or PBIX file for us to analyze.
Thanks,
Lydia Zhang