Hi Experts,

I have a report which I created  from the datadump in excel stored on my computer. Now in order to make the report dynamic, I want to connect it directly to the my DB and replace the existing Datasource with the new one. All the fields are same in  both Datasources as my Initial Dump is from my DB Only. How can I accomplish it in POWER BI.

Thanks

Deepak

1 ACCEPTED SOLUTION
ricardocamargos
Continued Contributor
Continued Contributor

Hi @drrai66,

 

You can try it:

 

Create a separated PBIX getting the data from the DB;

Click on "Advanced Editor" on "Edit Queries";

Copy the steps where it connects to the database;

Go to your original report, click in "Edit Queries" -> "Advanced Editor" and replace the source.

 

 

There is a reference here:

Change datasource in PBI

View solution in original post

1 REPLY 1
ricardocamargos
Continued Contributor
Continued Contributor

Hi @drrai66,

 

You can try it:

 

Create a separated PBIX getting the data from the DB;

Click on "Advanced Editor" on "Edit Queries";

Copy the steps where it connects to the database;

Go to your original report, click in "Edit Queries" -> "Advanced Editor" and replace the source.

 

 

There is a reference here:

Change datasource in PBI

Helpful resources

Announcements
June 2025 Power BI Update Carousel

Power BI Monthly Update - June 2025

Check out the June 2025 Power BI update to learn about new features.

June 2025 community update carousel

Fabric Community Update - June 2025

Find out what's new and trending in the Fabric community.