Forum Discussion
ChirSidh
Helper II
2 years agoRegionwise Allocation vs Available hours
in my power bi matrix table , i have employee in rows, allocation hours in columns, columns examples are North, South, East, West and total column. I have a available hours column as well. But the av...
lbendlin
Super User
2 years agoWhat's the primary key on the "Combined Resources" table?
ChirSidh
Helper II
2 years agoThere is UniqueresourceID in the resource table however duplicate entries are there. Does it work?
The main problem here is, for allocation hours , for a employee i have mulitple rows per week. But in the Avilable hours i have just for employee per week.