RAG Status for Due Date
Hi All, Pls help advise how to setup RAG status based on due date. If due date is before today, then Red If due date is between today and 30 days then Amber If due date is after days then Gree...
- 9 months ago
Hi gauravg3
RAG Status = SWITCH( TRUE(), ISBLANK([Due Date]), "No due date"), [Due Date] < TODAY(), "Red", [Due Date] >= TODAY() && [Due Date] < TODAY() + 30 , "Amber", "Green" )Regards
Phil
PhilipTreacy
9 months agoSuper User
Hi gauravg3
RAG Status =
SWITCH( TRUE(),
ISBLANK([Due Date]), "No due date"),
[Due Date] < TODAY(), "Red",
[Due Date] >= TODAY() && [Due Date] < TODAY() + 30 , "Amber",
"Green"
)
Regards
Phil