Hey there, I am trying to visualize the amount of overdue and intime taskes im comparison with new tasks coming up each month. I set the due date to the end of each month. Having this in the cha...
- 6 years ago
Hey Miguel,
thanks for your response!
I used a calender table which was linked to the dates in my data table 😉
I found out, that I had to change the type of my x-Axis to Category.
Now it works 🙂
Best regards,
Kim
v-kelly-msft
Community Support
6 years agoHi SchmitKS ,
It's a normal case,as you see below:
As you see,the X-axis shows July 2020,but the Quickinfo shows June 30,it's not a problem,when you have 2 days which are closer,such as June 30 and July 1,the related values will show together above the same X-axis dimension.
Best Regards,
Kelly