Hello,
I am stuck on a formula that I just can't seem to wrap my head around. I am attempting to build a visual that simply shows the estimated completion date based on current averages.
I currently have a measure that tells me it's going to take "n" working days to complete the project at the rate we are averaging.
What I'm attempting to do now is create a measure that returns this.
Today + The above measure (only counting weekdays) = what date?
Here are my current date table and formal that isn't really getting me the results I want.
Date Year Month Number Month Year Month Number Week Number Numeric Day of Week Month Year IsWorkingDay Binary Weekday
| Date | Year | Month Number | Month | Year Month Number | Week Number | Numeric Day of Week | Month Year | IsWorkingDay | Binary Weekday |
| 1/1/2020 | 2020 | 1 | January | 24240 | 1 | 3 | 20-Jan | TRUE | |
| 1/2/2020 | 2020 | 1 | January | 24240 | 1 | 4 | 20-Jan | TRUE | |
| 1/3/2020 | 2020 | 1 | January | 24240 | 1 | 5 | 20-Jan | TRUE | |
| 1/4/2020 | 2020 | 1 | January | 24240 | 1 | 6 | 20-Jan | FALSE | 1 |
| 1/5/2020 | 2020 | 1 | January | 24240 | 1 | 7 | 20-Jan | FALSE | 1 |
| 1/6/2020 | 2020 | 1 | January | 24240 | 2 | 1 | 20-Jan | TRUE | |
| 1/7/2020 | 2020 | 1 | January | 24240 | 2 | 2 | 20-Jan | TRUE | |
| 1/8/2020 | 2020 | 1 | January | 24240 | 2 | 3 | 20-Jan | TRUE | |
| 1/9/2020 | 2020 | 1 | January | 24240 | 2 | 4 | 20-Jan | TRUE | |
| 1/10/2020 | 2020 | 1 | January | 24240 | 2 | 5 | 20-Jan | TRUE | |
| 1/11/2020 | 2020 | 1 | January | 24240 | 2 | 6 | 20-Jan | FALSE | 1 |
| 1/12/2020 | 2020 | 1 | January | 24240 | 2 | 7 | 20-Jan | FALSE | 1 |
Hi Anonymous ,
try this
Estimated Finish Date with weekends = VAR Today = TODAY () VAR WorkingDaysThisWeek = 5 - WEEKDAY ( Today, 3 ) VAR WorkingDaysAfterThisWeek = [Estimated Working Days Till Completion] - WorkingDaysThisWeek VAR DaysAfterThisWeek = INT ( DIVIDE ( WorkingDaysAfterThisWeek, 5, 0 ) ) * 7 + MOD ( WorkingDaysAfterThisWeek, 5 ) RETURN IF ( [Estimated Working Days Till Completion] < WorkingDaysThisWeek, Today + [Estimated Working Days Till Completion], Today + WorkingDaysThisWeek + 2 + DaysAfterThisWeek )Hope this helps.
If I answered your question, please mark my post as solution, this will also help others.
Please give Kudos for support.
2 Replies
- mwegener
Most Valuable Professional
Hi Anonymous ,
try this
Estimated Finish Date with weekends = VAR Today = TODAY () VAR WorkingDaysThisWeek = 5 - WEEKDAY ( Today, 3 ) VAR WorkingDaysAfterThisWeek = [Estimated Working Days Till Completion] - WorkingDaysThisWeek VAR DaysAfterThisWeek = INT ( DIVIDE ( WorkingDaysAfterThisWeek, 5, 0 ) ) * 7 + MOD ( WorkingDaysAfterThisWeek, 5 ) RETURN IF ( [Estimated Working Days Till Completion] < WorkingDaysThisWeek, Today + [Estimated Working Days Till Completion], Today + WorkingDaysThisWeek + 2 + DaysAfterThisWeek )Hope this helps.
If I answered your question, please mark my post as solution, this will also help others.
Please give Kudos for support.
- JarroVGIT
Resident Rockstar
Hi Anonymous ,
Well this will work. Took me a while to figure it out, but I figured you can use RankX on a filtered datetable to get the desired output 🙂 I have used two tables, a datetable (DateTable) with column isWeekday (true or false) and the following test table (DaysToAdd):
The following measure gave me the desired result:
EndDateMeasure = IF(HASONEVALUE(DaysToAdd[Index]), VAR curDate = SELECTEDVALUE(DaysToAdd[StartDate]) VAR _daysToAdd = SELECTEDVALUE(DaysToAdd[DaysToAdd]) VAR _filteredDateTable = FILTER(DateTable, DateTable[Date] >= curDate && DateTable[isWeekday] = TRUE) RETURN MAXX(FILTER( ADDCOLUMNS(_filteredDateTable, "@rank", RANKX(_filteredDateTable, [Date],, ASC)), [@rank] = _daysToAdd + 1), [Date]))Pulling the testtable and the measure in a Table visual will give you this:
Well this was a fun question to answer! Hope it helps, let me know if you have any questions!
Kind regards
Djerro123
-------------------------------