Forum Discussion
Project SChedule Completion %
- 6 years ago
Anonymous ,
Yes - a separate table with that information will be able to help you get there!
- 6 years ago
Hi Anonymous ,
Is the profect # in slicer Select project a column in 'Start & End Dates' table? If not, please check the relationship between your table.
And you can try this calculate column and measure, maybe it is helpful.
Schedule Completion column = var monthsgone = 'Start & End Dates'[Today]-'Start & End Dates'[Start Date] var monthsremaining = 'Start & End Dates'[End Date] - 'Start & End Dates'[Start Date] var completed = DIVIDE(monthsgone,monthsremaining) return IF(completed>=1,1,completed)Schedule Completion measure = var monthsgone = MAX('Start & End Dates'[Today])-MAX('Start & End Dates'[Start Date]) var monthsremaining = MAX('Start & End Dates'[End Date]) - MAX('Start & End Dates'[Start Date]) var completed = DIVIDE(monthsgone,monthsremaining) return IF(completed>=1,1,completed)If it doesn’t meet your requirement, could you please provide a mockup sample based on fake data or describe the fields of each tables and the relations between tables simply?
It will be helpful if you can show us the exact expected result based on the tables.
Please upload your files to OneDrive For Business and share the link here. Please don't contain any Confidential Information or Real data in your reply.
BTW, pbix as attached.
Best regards,
Community Support Team _ zhenbw
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi Anonymous ,
Is the profect # in slicer Select project a column in 'Start & End Dates' table? If not, please check the relationship between your table.
And you can try this calculate column and measure, maybe it is helpful.
Schedule Completion column =
var monthsgone = 'Start & End Dates'[Today]-'Start & End Dates'[Start Date]
var monthsremaining = 'Start & End Dates'[End Date] - 'Start & End Dates'[Start Date]
var completed = DIVIDE(monthsgone,monthsremaining)
return
IF(completed>=1,1,completed)
Schedule Completion measure =
var monthsgone = MAX('Start & End Dates'[Today])-MAX('Start & End Dates'[Start Date])
var monthsremaining = MAX('Start & End Dates'[End Date]) - MAX('Start & End Dates'[Start Date])
var completed = DIVIDE(monthsgone,monthsremaining)
return
IF(completed>=1,1,completed)
If it doesn’t meet your requirement, could you please provide a mockup sample based on fake data or describe the fields of each tables and the relations between tables simply?
It will be helpful if you can show us the exact expected result based on the tables.
Please upload your files to OneDrive For Business and share the link here. Please don't contain any Confidential Information or Real data in your reply.
BTW, pbix as attached.
Best regards,
Community Support Team _ zhenbw
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hello v-zhenbw-msft ,
Please see below the screenshot. I have doubled checked the format of date columns and the dax but I am stil lgetting negative numbers in the column. Some are showing up correctly, but others aren't.