Forum Discussion
Project SChedule Completion %
- 6 years ago
Anonymous ,
Yes - a separate table with that information will be able to help you get there!
- 6 years ago
Hi Anonymous ,
Is the profect # in slicer Select project a column in 'Start & End Dates' table? If not, please check the relationship between your table.
And you can try this calculate column and measure, maybe it is helpful.
Schedule Completion column = var monthsgone = 'Start & End Dates'[Today]-'Start & End Dates'[Start Date] var monthsremaining = 'Start & End Dates'[End Date] - 'Start & End Dates'[Start Date] var completed = DIVIDE(monthsgone,monthsremaining) return IF(completed>=1,1,completed)Schedule Completion measure = var monthsgone = MAX('Start & End Dates'[Today])-MAX('Start & End Dates'[Start Date]) var monthsremaining = MAX('Start & End Dates'[End Date]) - MAX('Start & End Dates'[Start Date]) var completed = DIVIDE(monthsgone,monthsremaining) return IF(completed>=1,1,completed)If it doesn’t meet your requirement, could you please provide a mockup sample based on fake data or describe the fields of each tables and the relations between tables simply?
It will be helpful if you can show us the exact expected result based on the tables.
Please upload your files to OneDrive For Business and share the link here. Please don't contain any Confidential Information or Real data in your reply.
BTW, pbix as attached.
Best regards,
Community Support Team _ zhenbw
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi Anonymous ,
Are you trying to determine the schedule % completion of EACH schedule or of ALL the schedules combined? Based on your screenshot you are looking for the schedule % complete of each schedule. To determine schedule % complete, you would need to know the total duration of the schedule and how much of the duration is completed. Then, the calculation would be duration completed divided by total duration.
I would appreciate Kudos if my response was helpful. I would also appreciate it if you would Mark this As a Solution if it solved the problem. Thanks!
- Anonymous6 years agoNot applicable
Hello collinq ,
I am trying to put a card on my dashboard, so when a project a selected, it would show me the completion % of that project. I assumed when the project is selected from the slicer, it would automatically assume the start and finish when the filter is applied and then provide a % based on Today(). But right now I am getting just one number which is completion % for all the projects combined.
- collinq6 years agoSuper User
Hi Anonymous ,
So, I am not quite sure that is the correct definition of "% Complete".
Its sounds like you are actually trying to determine today's date from the max date of each project. To do that, I would add two columns - one for today. Which, in Power BI columns is actually
DateTime.LocalNow()
Then, you can get the maxdate from each project.
Then, you can subtract the now field from the maxdate.
- Anonymous6 years agoNot applicable
Still having some trouble.
When I use a dax for max date, I am getting just one max date which is July 2021.
Issue is the date Iget is from a software dump and it does not specify start and end date. A lot of these projects are from the past and some are 2019, 2020, 2021 with budgeted hours plugged in for months that haven't occured yet.