Project Online - Reporting on Date Changes

Hi All,

 

I am using Power BI connected to Project Online to report on Project progress. I would like to map the change in Finish Date across the different baselines. This is quite straightforward in Excel (screenshot below). 

 

Does anyone know how this could be replicated in Power BI?

 

(The column Baseline is the Original Finish Date.) 

 

Thanks,

Ashok

 

Line Graph showing date trends 

 

1 Reply

  • v-ljerr-msft's avatar
    v-ljerr-msft
    Microsoft Employee

    Hi Ashok1,

     

    I don't think there is an easy way to do it in Power BI currently, because only numeric column(but not a Date column) can be shown as Y axis on the line chart.

     

    In addition, here is a similar thread for your reference. :smileyhappy:

     

    Regards