Project Management - Dynamic Matrix Headers to show resources

HI friends,

for those in the projet management space, I have a tough nut to crack and i'm looking for your help. The goal is to analyse the allocation of tasks for a given resource and see whether they're overallocated. I'm looking to display this inforamtion via a line curve and a matrix visual 

 

Active variables: Start Date, End Date, Work effort (hours), task, responsible

 

Matrix Visual specs: 

- Columns would be displayed dynamically in the matrix, only the the dates between start/end date would appear

- Rows would show the tasks for a given resource

- Values would be the linear distribution of the hours over the duration
i.e. if a task has 100 hours of effort over a duration of 50 days = 2 hours per day that is applied linearly 

 

Curve spec:

- display the cummulative amount of work for a given resource per day

 

I would add a slicer to allow me to switch between resources

 

Bonus: If this can be switched to show weeks, months, quarters and years dynamically 

Let me know if you have any questions.

Thanks

- Jay

 

here's some sample data

 

Task TitleResourceStart_dateEnd_dateWork Effort
System No-Load Tests 5.6_3.6J Gouma15-May-2115-May-23100.00
End of Travel TestsJ Gouma15-May-2115-May-24200.00
Empty Rail car & Locomotive TestsJ Gouma15-May-2115-Nov-21300.00
(Dry) Tests J Gouma15-May-2115-Jul-22400.00
System trialF Pacico15-May-2015-May-2250.00
travel trialF Pacico15-Apr-2015-Apr-23100.00
empty bucket hopperF Pacico15-Mar-1915-Sep-1965.00
wet testsF Pacico15-Feb-1215-Apr-1355.00

1 Reply

  • v-xiaotang's avatar
    v-xiaotang
    Community Support

    Hi Anonymous 

    Based on your description,

    -

    Goal:

    to analyse the allocation of tasks for a given resource and see whether they're overallocated

    Visual:

    a line curve and a matrix visual

    -

    It would be better if you have a calendar table. Its easy to create one if you dont have. Your startdate is between 2012,2.15 2021,5,15, so I create a calendar table between 2012,2.15 2021,5,15 in my sample file.

    Then create 4 columns: week, month, quarter, year,

    Then we can switch to show weeks, months, quarters and years dynamically by using slicers as you want.

    -

    Sorry for not understanding your words Values would be the linear distribution of the hours over the duration i.e. if a task has 100 hours of effort over a duration of 50 days = 2 hours per day that is applied linearly 

    could your add more details? I dont know what should be put in the value of matrix.. so I just put work effort of your sample data into matrix.

    Besides, its also not clear that display the cummulative amount of work for a given resource per day”. Because there are several same resources and several different date periods for a given resource in your sample data. Do you want to summarize the amount from different periods? It would be better to give an example.

     

    Best Regards,

    Community Support Team _ Tang

    If this post helps, please consider Accept it as the solution to help the other members find it more quickly.