Forum Discussion
Progress Tracker
- Anonymous6 years ago
Hi Anonymous ,
Create something like this.
Calculated Column
ESTIMATED START DATE1 = VAR prevdate = CALCULATE ( MAX ( 'Table'[Begin Date] ), FILTER ( 'Table', 'Table'[Begin Date] < EARLIER ( 'Table'[Begin Date] ) ) ) VAR est = CALCULATE ( MAX ( 'Table'[Estimated Days] ), FILTER ( 'Table', 'Table'[Begin Date] = prevdate ) ) RETURN est + prevdateMeasures
Did it start on Estimate Date = VAR _datediff = DATEDIFF ( MAX ( 'Table'[ESTIMATED START DATE1] ), MAX ( 'Table'[Begin Date] ), DAY ) RETURN IF ( _datediff = 0, "Yes", "No" )Overdue = VAR _datediffactivitybeginend = DATEDIFF ( MAX ( 'Table'[Begin Date] ), MAX ( 'Table'[End Date] ), DAY ) RETURN IF ( _datediffactivitybeginend > MAX ( 'Table'[Estimated Days] ), "Overdue", "On-Time" )Project Overdue = var _beginactivity = CALCULATE(MIN('Table'[Begin Date]),ALL('Table'))---Date of 1st Task of project var _endactivity = CALCULATE(MAX('Table'[End Date]),ALL('Table')) var _datediffactivitybeginend = CALCULATE( DATEDIFF(_beginactivity,_endactivity,DAY)) RETURN IF(_datediffactivitybeginend <= SUM('Table'[Estimated Days]), "On-Time","OverDue")Regards,
Harsh NathaniAppreciate with a Kudos!! (Click the Thumbs Up Button)
Did I answer your question? Mark my post as a solution! - 6 years ago
Hi Anonymous ,
Maybe you can do like this.
IF suggested date = IF( MAX(Sheet5[Begin Date]) = DATE(2020, 8, 27), "Yes", "No" )How much progress = CALCULATE( COUNT(Sheet5[Task]), ALLEXCEPT( Sheet5, Sheet5[Task]) )If the activity is over = VAR x = DATEDIFF( MAX(Sheet5[Begin Date]), MAX(Sheet5[End Date]), DAY ) RETURN IF( x > MAX(Sheet5[Estimated Days]), "Yes", "No" )If the whole project is over due = VAR x = DATEDIFF( MAX(Sheet5[Begin Date]), MAX(Sheet5[End Date]), DAY ) RETURN IF( x > 84, "Yes", "No" )But to be honest, your data lacks completeness. If this is not what you want, please provide a more complete data table, including more key columns and duplicate rows.
Best regards,
Lionel ChenIf this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
HI Anonymous ,
You will need a end date for the tasks. That is not available.
How do I detemine how many days did the task Repair Engine take if I do not have the End Date?
I may be missing something. But pls share all information to help you.
Regards,
HN
you are right...
I added another column with the end date.
| Area | Task | Estimated Days | Begin Date | End Date |
| Logistics | Ship Parts | 7 | 8/27/2020 | 9/3/2020 |
| Maintenance | Repair Engines | 21 | 9/3/2020 | 9/24/2020 |
| Operations | Drill Well | 56 | 9/24/2020 | 11/19/2020 |
- Anonymous6 years agoNot applicable
Hi Anonymous ,
Create something like this.
Calculated Column
ESTIMATED START DATE1 = VAR prevdate = CALCULATE ( MAX ( 'Table'[Begin Date] ), FILTER ( 'Table', 'Table'[Begin Date] < EARLIER ( 'Table'[Begin Date] ) ) ) VAR est = CALCULATE ( MAX ( 'Table'[Estimated Days] ), FILTER ( 'Table', 'Table'[Begin Date] = prevdate ) ) RETURN est + prevdateMeasures
Did it start on Estimate Date = VAR _datediff = DATEDIFF ( MAX ( 'Table'[ESTIMATED START DATE1] ), MAX ( 'Table'[Begin Date] ), DAY ) RETURN IF ( _datediff = 0, "Yes", "No" )Overdue = VAR _datediffactivitybeginend = DATEDIFF ( MAX ( 'Table'[Begin Date] ), MAX ( 'Table'[End Date] ), DAY ) RETURN IF ( _datediffactivitybeginend > MAX ( 'Table'[Estimated Days] ), "Overdue", "On-Time" )Project Overdue = var _beginactivity = CALCULATE(MIN('Table'[Begin Date]),ALL('Table'))---Date of 1st Task of project var _endactivity = CALCULATE(MAX('Table'[End Date]),ALL('Table')) var _datediffactivitybeginend = CALCULATE( DATEDIFF(_beginactivity,_endactivity,DAY)) RETURN IF(_datediffactivitybeginend <= SUM('Table'[Estimated Days]), "On-Time","OverDue")Regards,
Harsh NathaniAppreciate with a Kudos!! (Click the Thumbs Up Button)
Did I answer your question? Mark my post as a solution!