how do I write dax formula to show all projects where End date is past due and “Project Status” doesn’t show “Complete” or “Cancelled”
- 4 years ago
&& works but the message i have is "DAX comparison operations do not support comparing values of type Text with values of type Date. Consider using the VALUE or FORMAT function to convert one of the values."
I am unable to use the new column for any visualization.
Best,
Yeboah
amitchandak
Super User
4 years agoYkankam , Try a measure like
Countrows(filter( Table, Not(isblank(Table[end date])) && [End Date] <= today() && not Table[Project Status] in {"Complete","Cancelled"}))
Ykankam
Helper I
4 years agoDo I format this a text? Because when I select this measure, it is unable to display on any visual