Forum Discussion
Power BI Project Management
how do I write dax formula to show all projects where End date is past due and “Project Status” doesn’t show “Complete” or “Cancelled”
&& works but the message i have is "DAX comparison operations do not support comparing values of type Text with values of type Date. Consider using the VALUE or FORMAT function to convert one of the values."
I am unable to use the new column for any visualization.
Best,
Yeboah
14 Replies
- YkankamHelper I
So basically, a dax formula that will create a new column by flagging a project either overdue or not overdue. Secondly, another dax formula that will create a new column a that will flag a past due project whose project status doesn't show "completed" or "cancelled", we can flag such projects as "past due - check"
- DhacdResolver III
Can you check whether the below code works or not?
Due status:Due Status= if([end]<=today(),"Overdue", "Not Overdue")Past Due check:
PastDueCheck = if([Due status]= "Overdue" and([Project Status]<> "Completed" or [Project Status]<> "Cancelled", "Past Due-Check")
Or you can do both in a single column.PastDueCheck= if([end]<=today() and ([Project Status]<> "Completed" or [Project Status]<> "Cancelled", "Past Due-Check")
Reply if there is any issues,
If this post helps, then please consider accepting it as the solution to help the other members find it more quickly.
Regards,Atma.
- YkankamHelper I
The dataset name is Bio Demand, just in case you will need it for the DAX
Thanks,
Yeboah
- amitchandakSuper User
Ykankam , Try a measure like
Countrows(filter( Table, Not(isblank(Table[end date])) && [End Date] <= today() && not Table[Project Status] in {"Complete","Cancelled"}))
- YkankamHelper I
Do I format this a text? Because when I select this measure, it is unable to display on any visual
- YkankamHelper I
Code was correct.I had to go to transform data and change [End] to a date format.