Power BI Project Management

how do I write dax formula to show all projects where End date is past due and “Project Status” doesn’t show “Complete” or “Cancelled”

  • && works but the message i have is "DAX comparison operations do not support comparing values of type Text with values of type Date. Consider using the VALUE or FORMAT function to convert one of the values."

     

    I am unable to use the new column for any visualization.

     

    Best,

     

    Yeboah

14 Replies

    • Ykankam's avatar
      Ykankam
      Helper I

      So basically, a dax formula that will create a new column by flagging a project either overdue or not overdue. Secondly, another dax formula that will create a new column a that will flag a past due project whose project status doesn't show  "completed" or "cancelled", we can flag such projects as "past due - check"

      • Dhacd's avatar
        Dhacd
        Resolver III

        Can you check whether the below code works or not?
        Due status:

         

        Due Status= if([end]<=today(),"Overdue", "Not Overdue")

         

        Past Due check:

         

        PastDueCheck = if([Due status]= "Overdue" and([Project Status]<> "Completed" or [Project Status]<> "Cancelled", "Past Due-Check")

         

         
        Or you can do both in a single column.

         

        PastDueCheck= if([end]<=today() and ([Project Status]<> "Completed" or [Project Status]<> "Cancelled", "Past Due-Check")

         


        Reply if there is any issues,

        If this post helps, then please consider accepting it as the solution to help the other members find it more quickly.

        Regards,

        Atma.

  • The dataset name is Bio Demand, just in case you will need it for the DAX

     

    Thanks,

     

    Yeboah

    • amitchandak's avatar
      amitchandak
      Super User

      Ykankam , Try a measure like

       

      Countrows(filter( Table, Not(isblank(Table[end date])) && [End Date] <= today() && not Table[Project Status] in {"Complete","Cancelled"}))

      • Ykankam's avatar
        Ykankam
        Helper I

        Do I format this a text? Because when I select this measure, it is unable to display on any visual

  • Code was correct.I had to go to transform data and change  [End] to a date format.