Hi I have a week start and a week end date. I have days of the week but no date is assigned to them. I would like a date assigned to the actual day that falls inbewteen the week start and end da...
- 3 years ago
Dev-13 ,
Easiest way is create a Calculated Column:
Date = SWITCH( TRUE(), [Day of Week] = "Monday", DayofWeek[Week Start] + 1, [Day of Week] = "Tuesday", DayofWeek[Week Start] + 2, [Day of Week] = "Wednesday", DayofWeek[Week Start] + 3, [Day of Week] = "Thursday", DayofWeek[Week Start] + 4, [Day of Week] = "Friday", DayofWeek[Week Start] + 5, [Day of Week] = "Saturday", DayofWeek[Week Start] + 6 )Trust this helps.
Regards,
rsbin
Community Champion
3 years agoDev-13 ,
Easiest way is create a Calculated Column:
Date = SWITCH(
TRUE(),
[Day of Week] = "Monday", DayofWeek[Week Start] + 1,
[Day of Week] = "Tuesday", DayofWeek[Week Start] + 2,
[Day of Week] = "Wednesday", DayofWeek[Week Start] + 3,
[Day of Week] = "Thursday", DayofWeek[Week Start] + 4,
[Day of Week] = "Friday", DayofWeek[Week Start] + 5,
[Day of Week] = "Saturday", DayofWeek[Week Start] + 6 )
Trust this helps.