Hi everybody,

 

I have a start date, end date and salary column for employees and I want to calculate phased salary. For instance, A earn 48000 per year. The start date is April 8 and the end date is July 1. The phased salary equals to 48000/12*2.25.  Any advice will be greatly appreciated. Thanks! 

1 ACCEPTED SOLUTION
v-chuncz-msft
Community Support
Community Support

@kenneth0596 ,

 

Try using DATEDIFF to add a calculated column.

 

Community Support Team _ Sam Zha
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

4 REPLIES 4
v-chuncz-msft
Community Support
Community Support

@kenneth0596 ,

 

Try using DATEDIFF to add a calculated column.

 

Community Support Team _ Sam Zha
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Ashish_Mathur
Super User
Super User

Why 2.25?  Explain.


Regards,
Ashish Mathur
http://www.ashishmathur.com
https://www.linkedin.com/in/excelenthusiasts/

I assume one month has four weeks so A works for 2 months and one week which is 2.25

Hi,

If someone starts on April 8, he works for 23 days in that month and thereafter for the 2 complete months.  How does that become 2.25?


Regards,
Ashish Mathur
http://www.ashishmathur.com
https://www.linkedin.com/in/excelenthusiasts/

Helpful resources

Announcements
November Carousel

Fabric Community Update - November 2024

Find out what's new and trending in the Fabric Community.

Live Sessions with Fabric DB

Be one of the first to start using Fabric Databases

Starting December 3, join live sessions with database experts and the Fabric product team to learn just how easy it is to get started.

Las Vegas 2025

Join us at the Microsoft Fabric Community Conference

March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount! Early Bird pricing ends December 9th.

Nov PBI Update Carousel

Power BI Monthly Update - November 2024

Check out the November 2024 Power BI update to learn about new features.