Hello,

 

I need some help creating performance calculations/project health metrics on my dashboard. I have a list of projects with scheduled start and end dates, and associated actual start and end dates. I need measures for how we are performing agaisnst the schedule (are we behind, on time, or ahead of schedule for each task). Any ideas would be helpful! Below is a sample excel document with the information. Thank you for your time and consideration!

DistrictTaskStart DateEnd DateDurationActual StartActual EndToday
OregonActual Timeline3/12/20198/10/2019151  7/12/2019
OregonGo Live7/17/20197/17/20190  7/12/2019
OregonDiscovery3/19/20193/19/201903/13/20193/13/20197/12/2019
OregonAsset Hierarchy3/19/20196/17/2019903/21/20196/20/20197/12/2019
OregonOMS Activity to Maximo Migration7/10/20197/10/201907/10/20197/10/20197/12/2019
OregonTraining Complete7/24/20197/24/20190  7/12/2019
OregonOn Site Support Start7/25/20198/17/201923  7/12/2019

2 Replies

  • vivran22's avatar
    vivran22
    Community Champion

    Anonymous 

     

    Hi,

     

    The exact requirement in terms of output is not clear from the description, however you may refer to the pbix file here

     

    Rgds,

    Vivek

     

    If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

     

  • vivran22's avatar
    vivran22
    Community Champion
    Hi,

    Has this been resolved?

    Rgds,
    Vivek