How do I show the percentage complete between a start date and today.
As an example, a project started on 6/1/2022 and ends on 9/30/2022. How do I show that today, 9/8/22 is **% complete (around 82%).
Solved! Go to Solution.
Hi ,
Use https://docs.microsoft.com/en-us/dax/datediff-function-dax
DATEDIFF function using Start Date ,End Date and Today
DATEDIFF(<Date1>, <Date2>, <Interval>)
Ritesh
Mark my post as a solution if it helped you| Munde and Kudis (Ladies and Gentlemen) I like your Kudos!! !!
My YT Channel Dancing With Data !! Connect on Linkedin !!Power BI for Tableau Users
Hi ,
Use https://docs.microsoft.com/en-us/dax/datediff-function-dax
DATEDIFF function using Start Date ,End Date and Today
DATEDIFF(<Date1>, <Date2>, <Interval>)
Ritesh
Mark my post as a solution if it helped you| Munde and Kudis (Ladies and Gentlemen) I like your Kudos!! !!
My YT Channel Dancing With Data !! Connect on Linkedin !!Power BI for Tableau Users
This is your chance to engage directly with the engineering team behind Fabric and Power BI. Share your experiences and shape the future.
Check out the June 2025 Power BI update to learn about new features.
User | Count |
---|---|
81 | |
76 | |
61 | |
37 | |
33 |
User | Count |
---|---|
99 | |
56 | |
50 | |
42 | |
40 |