Percentage Complete between date and today

How do I show the percentage complete between a start date and today. 

 

As an example, a project started on 6/1/2022 and ends on 9/30/2022. How do I show that today, 9/8/22 is **% complete (around 82%). 

1 ACCEPTED SOLUTION
ribisht17
Community Champion
Community Champion

Hi , 

Use https://docs.microsoft.com/en-us/dax/datediff-function-dax

 

DATEDIFF function using Start Date ,End Date and Today

 

DATEDIFF(<Date1>, <Date2>, <Interval>) 

 

Ritesh

Mark my post as a solution if it helped you| Munde and Kudis (Ladies and Gentlemen) I like your Kudos!! !!
My YT Channel Dancing With Data !! Connect on Linkedin !!Power BI for Tableau Users 

View solution in original post

1 REPLY 1
ribisht17
Community Champion
Community Champion

Hi , 

Use https://docs.microsoft.com/en-us/dax/datediff-function-dax

 

DATEDIFF function using Start Date ,End Date and Today

 

DATEDIFF(<Date1>, <Date2>, <Interval>) 

 

Ritesh

Mark my post as a solution if it helped you| Munde and Kudis (Ladies and Gentlemen) I like your Kudos!! !!
My YT Channel Dancing With Data !! Connect on Linkedin !!Power BI for Tableau Users 

Helpful resources

Announcements
Join our Fabric User Panel

Join our Fabric User Panel

This is your chance to engage directly with the engineering team behind Fabric and Power BI. Share your experiences and shape the future.

June 2025 Power BI Update Carousel

Power BI Monthly Update - June 2025

Check out the June 2025 Power BI update to learn about new features.

June 2025 community update carousel

Fabric Community Update - June 2025

Find out what's new and trending in the Fabric community.