Forum Discussion
PabloGiraldo
5 years agoHelper IV
Percent Complete from dates
Have asked this a few times and not sure if it is possible. Would like to create a percent complete using dates from my construction schedule to add to a card. (today's date minus project sta...
PabloGiraldo
5 years agoHelper IV
Thanks! Forgot to mention. The min would not work because my construction schedule starts a month or so before 8/24/2020. I already tried what you suggested but did not work in my case. Any idea how to go about this? Trying to find a way to pick a specific date from my table.
amitchandak
5 years agoSuper User
Can you share sample data and sample output in table format? Or a sample pbix after removing sensitive data.
- PabloGiraldo5 years agoHelper IV
Yes sir. See link below. Look at Table "ScheduleJan21"
- PabloGiraldo5 years agoHelper IV
amitchandak Maybe this is simpler to understand what i am trying to do. Thanks!
- DataZoe5 years agoMicrosoft Employee