Hi Alwaysactive You could achieve this by creating a custom measure for bar colors using SWITCH to assign the same color to the first and last total bars, then applying it in Data Colors. To rename "Total," create a custom column or measure using IF to replace "Total" with your desired label. Unfortunately, the default Waterfall Chart doesn’t support these changes directly.
If this post helped please do give a kudos and accept this as a solution
Thanks In Advance
Hi Alwaysactive
I wanted to check if you had the opportunity to review the information provided. Please feel free to contact us if you have any further questions. If my response has addressed your query, please accept it as a solution and give a 'Kudos' so other members can easily find it.