Need help with forecasting solution (I think i need the equivalent of SUMIFS)
Hi all, Im a relative newby to PowerBI. Im basically looking to create an invoicing forecast visualization based on a Project Online data-feed. I think i have the right idea on what i need to do ...
- Anonymous9 years ago
Hi acretney,
If your datasource is like the screenshot, you can add a calculated column to get summary value based on same project and milestone:
Proj/Milestone= CALCULATE(SUM(Table[VALUE]),Table[Project]=Earler(Table[Project]),Table[Milestone]=Earler(Table[Milestone]),ALLSELECT(Table))
Regards,
Xiaoxin Sheng
acretney
9 years agoFrequent Visitor
Hi Xiaoxin,
Apologies for my delayed reply. I've only had a chance to have a brief experiment with this but it looks as though you have solved my world! Will confirm tomorrow ;)
Kind regards
Alex
acretney
9 years agoFrequent Visitor
Apologies - delayed again. I confirm the solution however. Thanks very much