Microsoft Project Resource Allocation by Month
10-03-2022
06:25 PM
I have Power BI connected to Microsoft Project through PWA and for the projects I am managing I am trying to see how much work a resource has in a given month. Project tasks only have a start date and an end date and pulling one of those won't show the full picture for any month in between those two months. Below is what I am looking for:
Data Example:
Desired Result:
2 REPLIES 2
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-03-2022
06:51 PM

@bcummings12345 , You try if my blog can help
Static Method : https://amitchandak.medium.com/power-bi-power-query-vs-dax-months-between-range-df019cec823b
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content

Helpful resources
Announcements
Join us at the Microsoft Fabric Community Conference
March 31 - April 2, 2025, in Las Vegas, Nevada. Use code FABINSIDER for a $400 discount!
Power BI Monthly Update - February 2025
Check out the February 2025 Power BI update to learn about new features.

Recommendations
Subject | Author | Posted | |
---|---|---|---|
02-24-2024 06:48 AM | |||
10-02-2024 07:57 AM | |||
01-22-2025 10:19 AM | |||
11-11-2024 08:51 AM | |||
05-09-2024 02:33 PM |
Featured Topics
Top Solution Authors (Last Month)
User | Count |
---|---|
89 | |
85 | |
66 | |
52 | |
31 |
Top Kudoed Authors (Last Month)
User | Count |
---|---|
124 | |
114 | |
73 | |
65 | |
46 |