Microsoft Project Resource Allocation by Month
I have Power BI connected to Microsoft Project through PWA and for the projects I am managing I am trying to see how much work a resource has in a given month. Project tasks only have a start date an...
- 3 years ago
This solution uses a disconnected date table DimDateVisual (no relationships). This name will allow it to coexist with your main date table if you have one.
Create measure:
Resource Allocation = VAR vMinDate = MIN ( DimDateVisual[Date] ) VAR vMaxDate = MAX ( DimDateVisual[Date] ) VAR vTable = FILTER ( FactTable, FactTable[Start] <= vMaxDate && FactTable[End] >= vMinDate ) VAR vAmount = CALCULATE ( SUM ( FactTable[% Allocated] ), vTable ) VAR vResult = IF ( ISBLANK ( vAmount ), 0, vAmount ) RETURN vResultThe visual uses the Month column in DimDateVisual:
DataInsights
3 years agoSuper User
This solution uses a disconnected date table DimDateVisual (no relationships). This name will allow it to coexist with your main date table if you have one.
Create measure:
Resource Allocation =
VAR vMinDate =
MIN ( DimDateVisual[Date] )
VAR vMaxDate =
MAX ( DimDateVisual[Date] )
VAR vTable =
FILTER ( FactTable, FactTable[Start] <= vMaxDate && FactTable[End] >= vMinDate )
VAR vAmount =
CALCULATE ( SUM ( FactTable[% Allocated] ), vTable )
VAR vResult =
IF ( ISBLANK ( vAmount ), 0, vAmount )
RETURN
vResult
The visual uses the Month column in DimDateVisual: