Microsoft Gantt Visual for Date and Time

I'm trying to use Dates with Times to operate Microsofts Gantt Visual in PowerBI.

Here's my data. It's set as a Date/Time type.

When I load it into the visual it shows up like this.

How can I get it to consider the times and get the gantt to show the correct times?

 

Thanks,

 

Tamesh

  • Hi TameshDoobay - In Microsoft Gantt chart visual time is not getting recognized exclusively the time portion if the format of your date/time is not standard. Ensure that your Date/Time format is consistent and recognized by Power BI. If the Microsoft Gantt visual does not meet your requirements for time precision

     

     

     

     

    I have used custom chart Gantt Chart by MAQ Software or Gantt Chart by xViz which the time precesion is reflecting.

     

    Hope the above information helps. please check.

     

1 Reply

  • Hi TameshDoobay - In Microsoft Gantt chart visual time is not getting recognized exclusively the time portion if the format of your date/time is not standard. Ensure that your Date/Time format is consistent and recognized by Power BI. If the Microsoft Gantt visual does not meet your requirements for time precision

     

     

     

     

    I have used custom chart Gantt Chart by MAQ Software or Gantt Chart by xViz which the time precesion is reflecting.

     

    Hope the above information helps. please check.