Ashish,
Thanks. It's a great start I think. It doesn't report task g as 0% and when I look at it by project rather than task it doesn't calculate correctly. However, I'm hoping this gives me enough of an idea to do what I need. I'll let you know.
- GarnseyG6 years agoHelper I
This works for the individual tasks, but not for projects. Three of the four have the same percentages for each task (projects P1, P2, and P4) so the project level numbers are correct I think only because of this. But project P3 is wrong. There are 8 people who have reported time (yes some are the same person in different tasks but that doesn't matter) and 4 have time within the window. Project p3's percent should be 50%.
In total, 20 people (again the fact it was the same person in different tasks is not important) reported time and in 13 cases they were in the window, so 65%.