Forum Discussion
Marico
1 year agoHelper IV
Matrix
I have the following requirements from the user, but I am unsure how many are possible. Model Structure: The source and Target data come from two different database tables. The model also incl...
speedramps
1 year agoSuper User
Try this
delete the slicers table
Fux the relationship
fix the measure
fully op % = MAX(Target[fully % op])
use the Date[month year] in the slicer
Download my PBIX solution from Onedrive here
Please click [accept solution] and thumbs up button. Thank you