Forum Discussion
Matrix to display total days spent on the task - Conditional formatting based on late or on-time.
Chintan based on your reply, it means there must be data to show which stage each task is. Can you share some sample data in the table format?
- Chintan2 years agoFrequent Visitor
parry2k Please see below sample data. I have sequence the Stages from New to Manage in a raw. I mean first stage is New folllowed by Preparation and so on. Please note after manage stage, the task is completed. Here in below screenshot, Task 1 is delayed because it spend 6 days in Stage New and Stage New which first stage should be completed within 4 days from created date. By the end of 4th day, the team should have completed Stage New and update it's status to Stage Preparation. While Task 5 is on time beacuse within 19 days, it's already in Manage Stage.
New - 1 to 4 Days
Preparation - 5 to 8 DaysCalculation - 9 to 18 Days
Approved - 19 to 22 DaysManage - 23 to 28 Days
Hope it make sense.Many thanks