Matrix to display total days spent on the task - Conditional formatting based on late or on-time.

6 Replies

    • Chintan's avatar
      Chintan
      Frequent Visitor

      Thank Ritaf for your time and response.

       

      The videos are very helpful however I am not looking for Gantt Chart, it's kinda similar but what I want to achieve is still different to Gantt Chart and videos are all about Gantt Chart. 

      I want to write a DAX that count total days from the startdate and diaplay total days from Day 1 in the Matrix as shown in the screenshot. For example; first task in the screenshot took 21 days since startdate.
      Many thanks. 

  • Chintan I think I understood what you are looking for and I have some questions:

     

    - how do you find out if the task is on time or delayed?

    - what happens if it is more than 28 days?

    - what if tasks are already completed? Does that get added to it? If yes, if a task is already completed, do you still want to calculate the day based on today's date which in my opinion doesn't make sense?

     

    I think you need to look at the bigger picture and ask your questions accordingly.

    • Chintan's avatar
      Chintan
      Frequent Visitor

      parry2k Thank you for your response.

       

      -- Regarding on time or delayed, each task has five stages and it should be completed in 28 days. Stage 1 should be completed within 4 days of startdate, Stage 2 should be completed within 8 days of startdate, Stage 3 should be completed within 18 days of startdate, Stage 4 should be completed within 22 days of startdate and last Stage 5 should be completed within 28 days of startdate. For example; if Task 1 is in Stage 2 (which means it should be completed within 8 days of startdate) doesn't change it's status to Stage 3 in 8 days then it should be grey colour else blue colour.

       

      --  if it more than 28 days and still task is not completed we will just colour it grey from Day 1 and Day 28.

       

      -- No, completed task will be filter out and will not be included. So all good with Completed.

       

      Let me know if you have further question. I am excited for the solution. 

       

      Thank you ğŸ™‚

  • Chintan based on your reply, it means there must be data to show which stage each task is. Can you share some sample data in the table format?

    • Chintan's avatar
      Chintan
      Frequent Visitor

      parry2k Please see below sample data. I have sequence the Stages from New to Manage in a raw. I mean first stage is New folllowed by Preparation and so on. Please note after manage stage, the task is completed. Here in below screenshot, Task 1 is delayed because it spend 6 days in Stage New and Stage New which first stage should be completed within 4 days from created date. By the end of 4th day, the team should have completed Stage New and update it's status to Stage Preparation. While Task 5 is on time beacuse within 19 days, it's already in Manage Stage. 

       

      New - 1 to 4 Days
      Preparation - 5 to 8 Days

      Calculation - 9 to 18 Days
      Approved - 19 to 22 Days

      Manage - 23 to 28 Days



      Hope it make sense. 

       

      Many thanks