Matrix: Monthly Grand total for Project Timeline
I'm using the project timeline that Mr. Will Thompson posted some times ago. It's very useful to me. And I'm looking forward to having the grand total & subtotal. It just doesn't sum up the headc...
- Anonymous5 years ago
Hi Anonymous
Here is the solution.
Change the measure to this and you will see the total.Stage Text = var selectedDate = SELECTEDVALUE(Dates[Date]) var projectsBetweenDates = FILTER(Projects, Projects[Start Date] <= selectedDate && Projects[End Date] >= selectedDate) var numberProjects = COUNTROWS(projectsBetweenDates) var projectState = CALCULATE(MIN(Projects[Stage]), projectsBetweenDates) var headcount= IF(SELECTEDVALUE(Projects[Description])="",CALCULATE(SUM(Projects[Manpower]),projectsBetweenDates),CALCULATE(MAX(Projects[Manpower]),projectsBetweenDates)) return IF(projectState<>"", headcount, " ")Find the pbix attached after signature.
Anonymous
5 years agoNot applicable
Hi Anonymous
Here is the solution.
Change the measure to this and you will see the total.
Stage Text =
var selectedDate = SELECTEDVALUE(Dates[Date])
var projectsBetweenDates = FILTER(Projects, Projects[Start Date] <= selectedDate && Projects[End Date] >= selectedDate)
var numberProjects = COUNTROWS(projectsBetweenDates)
var projectState = CALCULATE(MIN(Projects[Stage]), projectsBetweenDates)
var headcount= IF(SELECTEDVALUE(Projects[Description])="",CALCULATE(SUM(Projects[Manpower]),projectsBetweenDates),CALCULATE(MAX(Projects[Manpower]),projectsBetweenDates))
return IF(projectState<>"", headcount, " ")
Find the pbix attached after signature.
- Anonymous5 years agoNot applicable
Anonymous , it works perfectly! Didn't know it's so easy!
Thank you for being so helpful.