Making a risk report from MS Project Online - creating visuals
I am a new user and am trying to create a risk report on PowerBI using information about projects which has been imported from MS Project Online. 1. I want to calculate the number of risks per proje...
- 3 years ago
Hi Charday ,
Please follow these steps:
(1)Create a measure to calculate the number of risks per project.
Number of risks = CALCULATE(COUNT(Risk[ID]),FILTER(ALL(Risk),Risk[Project ID] = MAX(Project[ID])))(2) Create a calculated column to determine whether the project is at risk
ISRISK = IF([Number of risks]>0,"RISK","NO RISK")(3) Final output
Best Regards,
Gallen Luo
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
v-jialluo-msft
Community Support
3 years agoHi Charday ,
Please follow these steps:
(1)Create a measure to calculate the number of risks per project.
Number of risks = CALCULATE(COUNT(Risk[ID]),FILTER(ALL(Risk),Risk[Project ID] = MAX(Project[ID])))
(2) Create a calculated column to determine whether the project is at risk
ISRISK = IF([Number of risks]>0,"RISK","NO RISK")
(3) Final output
Best Regards,
Gallen Luo