Hi MAQ 

 

In my example. the Project 1 is  divided in two phases

ProjectIDFeha InicioFecha Fin
Project 1131/01/201910/02/2019
Project 1201/03/201921/03/2019
Project 2331/01/201910/02/2019
Project 3431/01/201910/02/2019
Project 4531/01/201910/02/2019
Project 5631/01/201910/02/2019

 

I  would like to show Project 1 in one unique line, showing the timeline bar for each phase. Somenthing similiar like in this example:

 

 

In Gantt 1.14.3 there is an option called "Group Task" that makes this simple. Is there any similar option in MAQ Gantt to do this?

https://www.dropbox.com/s/wiq27b696u1u1m8/Gantt%20project.pbix?dl=0

 

Thank you very much

Reuben

 

  • Anonymous's avatar
    Anonymous
    7 years ago

    Hi Anonymous ,

    Nope, this visual not support this. If you have multiple category records, it will show as multiple line on visual instead of group them to one category.

    Regards,

    Xiaoxin Sheng

  • Hello Anonymous ,

     

    The current version of Gantt Chart by MAQ Software does not support showing multiple bars in a row.

    We have added your request to our backlog.

     

    We will notify you on this thread when we enhance the visual with this feature.

     

    Thanks.

2 Replies

  • Anonymous's avatar
    Anonymous
    Not applicable

    Hi Anonymous ,

    Nope, this visual not support this. If you have multiple category records, it will show as multiple line on visual instead of group them to one category.

    Regards,

    Xiaoxin Sheng

  • MAQSupport's avatar
    MAQSupport
    Solution Supplier

    Hello Anonymous ,

     

    The current version of Gantt Chart by MAQ Software does not support showing multiple bars in a row.

    We have added your request to our backlog.

     

    We will notify you on this thread when we enhance the visual with this feature.

     

    Thanks.