Looking up the Latest Value for a Given Task Name

Hello, I use Power BI to compile information from multiple projects entered into Microsoft Project (MSP). The project name is associated with a Projects table, and date-level information is associate...
  • nck13441's avatar
    nck13441
    8 years ago

    This didn't quite work, but you set me on the right path! Here's what ended up working:

     

    60% Turn In = CALCULATE ( MAX ( Tasks[FinishDate]), Tasks[taskname] = "Work on Design - 60%")

     

    Thank you!