This time we’re going bigger than ever. Fabric, Power BI, SQL, AI and more. We're covering it all. You won't want to miss it.
Learn moreLevel up your Power BI skills this month - build one visual each week and tell better stories with data! Get started
Hi Everyone!
I´m very new to Power BI and as a part of my project I have been asked to build a Gantt chart.I am using lingaro and it has worked well for me. I only have two questions that I have not been able to solve by myself.
1. Is there a way to order my projects the way I want them? By default it sorts them by alphabet, I tried to put in numbers but it recognizes numbers greater than 10 as 1 😞
2. When I download my gantt to power point, I lose the visualization.
Please if someone could help me with these questions it would help me a lot.
Thank you very much!
Solved! Go to Solution.
Hi @CataCC ,
For question 1:
Based on my test, currently the Lingaro Gantt chart could not support the sort feature. You can use the Projects as Legend and the number column as Y -axis to 'sort' by the number.
For question 2:
Please pay attentation to this limitation about exporting to Power Point:
The Lingaro Gantt chart is not a certified visual so it could not be exported to power point.
Lingaro does not have a blue badge
You can consider using other Gantt charts which are certificated to replace it if you need to export it to power point.
Best Regards,
Community Support Team _ Yingjie Li
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Hi @CataCC ,
For question 1:
Based on my test, currently the Lingaro Gantt chart could not support the sort feature. You can use the Projects as Legend and the number column as Y -axis to 'sort' by the number.
For question 2:
Please pay attentation to this limitation about exporting to Power Point:
The Lingaro Gantt chart is not a certified visual so it could not be exported to power point.
Lingaro does not have a blue badge
You can consider using other Gantt charts which are certificated to replace it if you need to export it to power point.
Best Regards,
Community Support Team _ Yingjie Li
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Check out the April 2026 Power BI update to learn about new features.
Sign up to receive a private message when registration opens and key events begin.
If you have recently started exploring Fabric, we'd love to hear how it's going. Your feedback can help with product improvements.
| User | Count |
|---|---|
| 35 | |
| 32 | |
| 25 | |
| 22 | |
| 18 |
| User | Count |
|---|---|
| 67 | |
| 36 | |
| 32 | |
| 25 | |
| 23 |