Forum Discussion
Lingaro Gantt Chart
Hi Everyone!
I´m very new to Power BI and as a part of my project I have been asked to build a Gantt chart.I am using lingaro and it has worked well for me. I only have two questions that I have not been able to solve by myself.
1. Is there a way to order my projects the way I want them? By default it sorts them by alphabet, I tried to put in numbers but it recognizes numbers greater than 10 as 1 😞
2. When I download my gantt to power point, I lose the visualization.
Please if someone could help me with these questions it would help me a lot.
Thank you very much!
Hi CataCC ,
For question 1:
Based on my test, currently the Lingaro Gantt chart could not support the sort feature. You can use the Projects as Legend and the number column as Y -axis to 'sort' by the number.
For question 2:
Please pay attentation to this limitation about exporting to Power Point:
- Custom visuals that haven't been certified) aren't supported.
The Lingaro Gantt chart is not a certified visual so it could not be exported to power point.
Lingaro does not have a blue badge
You can consider using other Gantt charts which are certificated to replace it if you need to export it to power point.
Best Regards,
Community Support Team _ Yingjie Li
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
1 Reply
- v-yingjl
Community Support
Hi CataCC ,
For question 1:
Based on my test, currently the Lingaro Gantt chart could not support the sort feature. You can use the Projects as Legend and the number column as Y -axis to 'sort' by the number.
For question 2:
Please pay attentation to this limitation about exporting to Power Point:
- Custom visuals that haven't been certified) aren't supported.
The Lingaro Gantt chart is not a certified visual so it could not be exported to power point.
Lingaro does not have a blue badge
You can consider using other Gantt charts which are certificated to replace it if you need to export it to power point.
Best Regards,
Community Support Team _ Yingjie Li
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.