SCNCKS1
Helper I
Helper I

Legend for a matrix timeline in powerbi

Hi - i created a timeline matrix in powerbi that shows planned and actual and the overlap (photo below). I used the code below the photo to populate the table. I am wondering what is the best way to create a legend that explains the red is planned, blue is actual and purple is where they overlap. All of the videos use a status to create a dynamic legend, but I don't have a status, thought i could create one based on the dates in my table if necessary. The data is in a stand-alone table with 2 relationships, one to date, and one to project. Any ideas on the most efficient way to create this?

 

SCNCKS1_0-1695303297530.png

SCNCKS1_1-1695303574465.png

 

Gantt =
VAR EST_StartDate =
CALCULATE(
    Min(PROD_COST_TABLE[Dates]),
    REMOVEFILTERS('Date'),
    PROD_COST_TABLE[DA_Est_Qty_Complete] >0
    )

VAR EST_EndDate =
CALCULATE(
    MAX(PROD_COST_TABLE[Dates]),
    REMOVEFILTERS('Date'),
    PROD_COST_TABLE[DA_Est_Qty_Complete] >0
    )
VAR EST_ProjectPeriod =
MIN('Date'[WeekEnding]) >= EST_StartDate
&& Max('Date'[WeekEnding]) <= EST_EndDate

VAR Actual_StartDate =
CALCULATE(
    Min(PROD_COST_TABLE[Dates]),
    REMOVEFILTERS('Date'),
    PROD_COST_TABLE[Qty_Complete] >0
    )
VAR Actual_EndDate =
CALCULATE(
    MAX(PROD_COST_TABLE[Dates]),
    REMOVEFILTERS('Date'),
    PROD_COST_TABLE[Qty_Complete] >0
    )
VAR Actual_ProjectPeriod =
MIN('Date'[WeekEnding]) >= Actual_StartDate
&& Max('Date'[WeekEnding]) <= Actual_EndDate

VAR EST_Actual_ProjectPeriod =
MIN('Date'[WeekEnding]) >= Actual_StartDate && MIN('Date'[WeekEnding]) >= Est_StartDate
&& Max('Date'[WeekEnding]) <= Actual_EndDate && Max('Date'[WeekEnding]) <= Est_EndDate

VAR RESULT =
SWITCH(
    TRUE(),
    EST_Actual_ProjectPeriod,3,
    Actual_ProjectPeriod,2,
    EST_ProjectPeriod,1
    )

RETURN
RESULT
2 REPLIES 2
christinepayton
Super User
Super User

You could create a dimension table with "enter data" to create the legend values you are using as rules, then relate it to the field you are using in your rules (or add a conditional column on the values in PQ) and drop it in the legend well. 

I don't see the legend well in the matrix visual or did i misunderstand your suggestion?

Helpful resources

Announcements
November Carousel

Fabric Community Update - November 2024

Find out what's new and trending in the Fabric Community.

Live Sessions with Fabric DB

Be one of the first to start using Fabric Databases

Starting December 3, join live sessions with database experts and the Fabric product team to learn just how easy it is to get started.

Las Vegas 2025

Join us at the Microsoft Fabric Community Conference

March 31 - April 2, 2025, in Las Vegas, Nevada. Use code MSCUST for a $150 discount! Early Bird pricing ends December 9th.

Nov PBI Update Carousel

Power BI Monthly Update - November 2024

Check out the November 2024 Power BI update to learn about new features.