Legend for a matrix timeline in powerbi

Hi - i created a timeline matrix in powerbi that shows planned and actual and the overlap (photo below). I used the code below the photo to populate the table. I am wondering what is the best way to create a legend that explains the red is planned, blue is actual and purple is where they overlap. All of the videos use a status to create a dynamic legend, but I don't have a status, thought i could create one based on the dates in my table if necessary. The data is in a stand-alone table with 2 relationships, one to date, and one to project. Any ideas on the most efficient way to create this?

 

SCNCKS1_0-1695303297530.png

SCNCKS1_1-1695303574465.png

 

Gantt =
VAR EST_StartDate =
CALCULATE(
    Min(PROD_COST_TABLE[Dates]),
    REMOVEFILTERS('Date'),
    PROD_COST_TABLE[DA_Est_Qty_Complete] >0
    )

VAR EST_EndDate =
CALCULATE(
    MAX(PROD_COST_TABLE[Dates]),
    REMOVEFILTERS('Date'),
    PROD_COST_TABLE[DA_Est_Qty_Complete] >0
    )
VAR EST_ProjectPeriod =
MIN('Date'[WeekEnding]) >= EST_StartDate
&& Max('Date'[WeekEnding]) <= EST_EndDate

VAR Actual_StartDate =
CALCULATE(
    Min(PROD_COST_TABLE[Dates]),
    REMOVEFILTERS('Date'),
    PROD_COST_TABLE[Qty_Complete] >0
    )
VAR Actual_EndDate =
CALCULATE(
    MAX(PROD_COST_TABLE[Dates]),
    REMOVEFILTERS('Date'),
    PROD_COST_TABLE[Qty_Complete] >0
    )
VAR Actual_ProjectPeriod =
MIN('Date'[WeekEnding]) >= Actual_StartDate
&& Max('Date'[WeekEnding]) <= Actual_EndDate

VAR EST_Actual_ProjectPeriod =
MIN('Date'[WeekEnding]) >= Actual_StartDate && MIN('Date'[WeekEnding]) >= Est_StartDate
&& Max('Date'[WeekEnding]) <= Actual_EndDate && Max('Date'[WeekEnding]) <= Est_EndDate

VAR RESULT =
SWITCH(
    TRUE(),
    EST_Actual_ProjectPeriod,3,
    Actual_ProjectPeriod,2,
    EST_ProjectPeriod,1
    )

RETURN
RESULT
2 REPLIES 2
christinepayton
Solution Sage
Solution Sage

You could create a dimension table with "enter data" to create the legend values you are using as rules, then relate it to the field you are using in your rules (or add a conditional column on the values in PQ) and drop it in the legend well. 

I don't see the legend well in the matrix visual or did i misunderstand your suggestion?

Helpful resources

Announcements
Fabric Community Conference

Microsoft Fabric Community Conference

Join us at our first-ever Microsoft Fabric Community Conference, March 26-28, 2024 in Las Vegas with 100+ sessions by community experts and Microsoft engineering.

February 2024 Update Carousel

Power BI Monthly Update - February 2024

Check out the February 2024 Power BI update to learn about new features.

Fabric Career Hub

Microsoft Fabric Career Hub

Explore career paths and learn resources in Fabric.

Fabric Partner Community

Microsoft Fabric Partner Community

Engage with the Fabric engineering team, hear of product updates, business opportunities, and resources in the Fabric Partner Community.