Iterating and comparing rows
Hello,
Where can I find the hours?
Determining projected completion dates, based on the sum of the hours of tasks ranked above them
Also, how is the projected end date computed? I am assuming that it is 7 (x rank-1) days from rank1 project.
Hi danextian - thanks for your help.
The hours = 8 hours x number of working days.
The projected completion date is the end of the previously ranked project + working days. For example ID 5, top ranked project finishes on 15/08/22. ID 5 second ranked project then has a completion date of 15/8/22 + 5 working days being 22/8/22 (due to weekend days).
- danextian4 years agoSuper User
I am confused how the rank is calculated. For ID5, it appears that they're ranked by priority. For 7, they are ranked by Due Date.
- DebbieK4 years agoHelper I
Hi danextian,
The logic is to rank by due date, then check if a higher prioirity task is not ontime and if so promote it up the ranks.
For ID 7 they are ranked by due date, and the higher priority task is on time, so no changes are needed.
I've played out the example process for ID 5 below.
STEP 1 - Sort by due date
AssignedToID Due Date Priority (999 = highest) WorkingDaysRemaining 5 1/08/2022 200 5 5 15/08/2022 900 10 5 20/08/2022 500 5 6 1/08/2022 100 5 6 13/08/2022 500 5 6 15/08/2022 500 5 7 5/08/2022 100 7 7 10/08/2022 100 4 7 30/08/2022 900 2 STEP 2 - Iterate and check whether on time, promote if needed.
EG.
Row 2, ONTIME = N, so check whether Row 2 is a higher priority than Row 1.
900 > 200 so move Row 2 up rank.
AssignedToID Due Date Priority (999 = highest) WorkingDaysRemaining ProjectedEndDate Ontime 5 1/08/2022 200 5 8/08/2022 N 5 15/08/2022 900 10 22/08/2022 N 5 20/08/2022 500 5 29/08/2022 N 6 1/08/2022 100 5 8/08/2022 N 6 13/08/2022 500 5 15/08/2022 N 6 15/08/2022 500 5 22/08/2022 Y 7 5/08/2022 100 7 10/08/2022 N 7 10/08/2022 100 4 16/08/2022 N 7 30/08/2022 900 2 18/08/2022 Y Then EG
Row 3, ONTIME = N, so check whether Row 3 is higher priority than Row 2.
Priority 500> 200, so move Row 3 up rank
ONTIME still = No
Check whether higher priority than Row 1
Priority 500 < 900 so do not move higher.
AssignedToID Due Date Priority (999 = highest) WorkingDaysRemaining ProjectedEndDate Ontime 5 15/08/2022 900 10 15/08/2022 Y 5 1/08/2022 200 5 22/08/2022 N 5 20/08/2022 500 5 29/08/2022 N 6 1/08/2022 100 5 8/08/2022 N 6 13/08/2022 500 5 15/08/2022 N 6 15/08/2022 500 5 22/08/2022 Y 7 5/08/2022 100 7 10/08/2022 N 7 10/08/2022 100 4 16/08/2022 N 7 30/08/2022 900 2 18/08/2022 Y Finished iteration of ID5
AssignedToID Due Date Priority (999 = highest) WorkingDaysRemaining Rank ProjectedEndDate Ontime 5 15/08/2022 900 10 1 15/08/2022 Y 5 20/08/2022 500 5 2 22/08/2022 N 5 1/08/2022 200 5 3 29/08/2022 N 6 1/08/2022 100 5 8/08/2022 N 6 13/08/2022 500 5 15/08/2022 N 6 15/08/2022 500 5 22/08/2022 Y 7 5/08/2022 100 7 10/08/2022 N 7 10/08/2022 100 4 16/08/2022 N 7 30/08/2022 900 2 18/08/2022 Y - danextian4 years agoSuper User
In step 2, how would one know whether a project is on-time or not? Also in row 2, 15/8 + 10 workdays shouldn't that be 29/8?