Forum Discussion

Anonymous's avatar
Anonymous
Not applicable
7 years ago

Incorrect Matrix Totals

Hi, I know this has probably been asked many times before but I can't find a solution for my scenario.


I need to show timeslip data for consultants. The company either bills project phases at "Fixed Fee" (fixed price for the project phase with a total number of days, even if they work more than this then they can't bill for it) or "Day Rate" (standard day rate * days worked)

 

However my matrix totals are not adding up correctly - it seems to  be including the sub row "34,725" rather than the total for that project task "35,250".

 

I've included a screenshot and my DAX below. Can anyone help? I don't know if i'm missing something..

 

DAX: https://i.ibb.co/0CPyYM9/2.png

Matrix: https://i.ibb.co/Kr7Fvxq/1.png

 

Thanks.

 

 

1 Reply