I think your calculation of amount per day is incorrect. For the first project, it should be 100000/121 = 826.4463 and not 100000/120=833.3333. You may download my PBI file from here.
Hope this helps.
- EdwardWer2 years agoFrequent Visitor
Ashish:
Hello. I could not download the file with the link you provided.
Can you please advise what change you made to the DAX Measure "MonthAmount"?
Thanks,
Edward
- Ashish_Mathur2 years agoSuper User
Hi,
I do not have that file anymore. Describe the question and show the expected result.
- EdwardWer2 years agoFrequent Visitor
Ashish:
The image you posted, shown below, had the correct "Total values".
The values in the file uploaded by someone else (URL below) had incorrect Total values, please see the screen shot below.
I was curious how you corrected this.
Thanks,
Edward
- Ashish_Mathur2 years agoSuper User
Hi,
I cannot understand your question. Offer a simple explanation and show the expected result.