How to spread value between two dates ?
Hi everyone, I need some help on my Power BI. I am trying to spread the value of a project over several months, to know exactly how much I will have to produce every month. For exemple, if I...
Ashish_Mathur
6 years agoSuper User
Hi,
I think your calculation of amount per day is incorrect. For the first project, it should be 100000/121 = 826.4463 and not 100000/120=833.3333. You may download my PBI file from here.
Hope this helps.
EdwardWer
2 years agoFrequent Visitor
Ashish:
Hello. I could not download the file with the link you provided.
Can you please advise what change you made to the DAX Measure "MonthAmount"?
Thanks,
Edward
- Ashish_Mathur2 years agoSuper User
Hi,
I do not have that file anymore. Describe the question and show the expected result.