How to Create Gantt Chart Visual With Multiple Milestones On One Line?

Suppose I have the following data structure (from an Excel file but I guess this doesn't really matter here) Name MS1 MS2 MS3 Task 1 15.03.2021 30.06.2021 30.10.2021 Task 2 01.02.202...
  • mahoneypat's avatar
    5 years ago

    Please check out the As Timeline visual.  I unpivoted your data and tried that.  Key thing is to uncheck the Stacked option in the formatting options.

     

     

    Regards,

    Pat