Join us at FabCon Atlanta from March 16 - 20, 2026, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.
Register now!Vote for your favorite vizzies from the Power BI Dataviz World Championship submissions. Vote now!
Hi There
Got a parser from Primavera P6.
I can calculate the number of FS, SS, SF & FF logics as you can see in the attached file. I need to Count the numbers right after FS, SS, SF & FF logics.
Power BI files & Excel data are also attached. The overall lags are 4574 & later I need to calculate Lags that are greater than 10 the answer for this is 93.
Lag Counts BI File & Data in Excel
Solved! Go to Solution.
I could not download your PBIX due to restrictions on my laptop. For now, I can recommend splitting or extracting the data in Power Query and then you can do a count of the numbers of that column accordingly.
I could not download your PBIX due to restrictions on my laptop. For now, I can recommend splitting or extracting the data in Power Query and then you can do a count of the numbers of that column accordingly.
Hi Saud
I have uploaded it again, please check.
I have tried splitting the data but was unable to fix it.
Regards
Allow me sometime, as I am working on my own project will take sometime to complete it.
Just I need to look at the advanced feature and all more than 25 columns.
"I can recommend splitting or extracting the data in Power Query and then you can do a count of the numbers of that column accordingly."
Vote for your favorite vizzies from the Power BI World Championship submissions!
If you love stickers, then you will definitely want to check out our Community Sticker Challenge!
Check out the January 2026 Power BI update to learn about new features.
| User | Count |
|---|---|
| 64 | |
| 51 | |
| 46 | |
| 23 | |
| 19 |
| User | Count |
|---|---|
| 136 | |
| 110 | |
| 50 | |
| 32 | |
| 29 |