How to Count Numbers (Lag) after FS, SS, SF & FF from Primavera P6 Data?

Hi There

 

Got a parser from Primavera P6.

 

I can calculate the number of FS, SS, SF & FF logics as you can see in the attached file. I need to Count the numbers right after FS, SS, SF & FF logics.
Power BI files & Excel data are also attached. The overall lags are 4574 & later I need to calculate Lags that are greater than 10 the answer for this is 93.

 

Lags.png

Lag Counts BI File  & Data in Excel  

1 ACCEPTED SOLUTION
saud968
Memorable Member
Memorable Member

I could not download your PBIX due to restrictions on my laptop. For now, I can recommend splitting or extracting the data in Power Query and then you can do a count of the numbers of that column accordingly. 

View solution in original post

4 REPLIES 4
saud968
Memorable Member
Memorable Member

I could not download your PBIX due to restrictions on my laptop. For now, I can recommend splitting or extracting the data in Power Query and then you can do a count of the numbers of that column accordingly. 

Hi Saud

I have uploaded it again, please check. 
I have tried splitting the data but was unable to fix it.

Regards

Allow me sometime, as I am working on my own project will take sometime to complete it.

Just I need to look at the advanced feature and all more than 25 columns.

 

"I can recommend splitting or extracting the data in Power Query and then you can do a count of the numbers of that column accordingly."

Helpful resources

Announcements
Power BI DataViz World Championships

Power BI Dataviz World Championships

Vote for your favorite vizzies from the Power BI World Championship submissions!

Sticker Challenge 2026 Carousel

Join our Community Sticker Challenge 2026

If you love stickers, then you will definitely want to check out our Community Sticker Challenge!

January Power BI Update Carousel

Power BI Monthly Update - January 2026

Check out the January 2026 Power BI update to learn about new features.

FabCon Atlanta 2026 carousel

FabCon Atlanta 2026

Join us at FabCon Atlanta, March 16-20, for the ultimate Fabric, Power BI, AI and SQL community-led event. Save $200 with code FABCOMM.